Saudi Arabia
Saudi MEP Mega-Project Mobilization
The project required 280 MEP workers to mobilise in staggered waves. A total of 266 electricians, HVAC technicians, plumbers and site supervisors were deployed while a multi-country quality-control dossier was finalised for the main contractor.
Execution protocol
- Pre-issue requirement validation and local labour quota check
- Candidate pool built from India and Nepal with GCC-experienced resumes only
- In-person trade testing at metro hubs with employer sign-off
- Visa and medical completed in staged waves to avoid site saturation
- Arrival scheduling matched to installation milestones and accommodation readiness
Verification & compliance
100% QVP credential review + practical trade benchmarks for electrical and HVAC work + employer sign-off on all WPS and HSE documents.
Client classification: Tier-1 Electro-Mechanical EPC Contractor
Sourcing corridors: india, nepal
Mobilization funnel
| Metric | Value |
|---|---|
| Total Requisition | 280 |
| Cvs Screened | 1842 |
| Trade Tested In Person | 368 |
| Client Selected | 276 |
| Visas Stamped | 270 |
| Deployed Total | 266 |
| On Schedule Rate | 96% |
| Total Mobilization Days | 52 |
| Ninety Day Retention Rate | 98.7% |
Roles deployed
| Role | Headcount | Trade-test specifics |
|---|---|---|
| Electricians | 120 | LV panel, cable termination, load testing and safety sign-off |
| HVAC Technicians | 56 | Chiller plant and AHU fault-finding plus refrigerant handling |
| Plumbers | 72 | Water network testing and pressure-check simulation |
| Site Supervisors and Foremen | 18 | Documentation, HSE and defect-closure review |